The fence post concrete calculator estimates the space left around a post. It starts with the volume of a round hole, subtracts the part of the post embedded in concrete, and multiplies by the number of matching holes. Measure the actual post face or diameter and its embedded length.
Calculate concrete for fence post holes using hole diameter, depth and quantity. Subtract the volume displaced by the embedded round or rectangular post. Work from the measurements for your actual project before you check price. If another material belongs on the same order, work out its quantity separately. For companion estimates and measuring advice, see How to Read Concrete Yield and Material Coverage Labels, Cubic Feet to Cubic Yards: Material Volume Conversion, Concrete Bag Calculator, Footing Concrete Calculator. Read the CubicPilot calculation methodology for rounding, units and material assumptions.
How do you use this calculator?
- Select the shape if the tool offers a choice, then enter the primary measurements with their units.
- Enter the product’s actual label value when the form requests a yield, a package count, coverage or stock size.
- Choose an allowance explicitly. Read the measured and adjusted quantities before rounding any supplier order.
What should you enter?
- Hole diameter
- Full inside diameter of the concrete-filled hole. Measure straight across the center.
- Hole depth
- Thickness or depth of the measured material. Measure only the layer being estimated and confirm the unit before entering.
- Number of holes
- Number of identical units. Make a separate entry for each distinct size.
- Post width / round diameter
- Actual width of a rectangular post or diameter of a round post. Measure the physical face and use the selected post shape.
- Square post height
- Other face dimension of a rectangular post. Measure the adjacent face where the cross section differs.
- Embedded post depth
- Length of the post actually inside the concrete. Measure the overlap with the concrete-filled part of the hole.
- Waste / allowance
- The percentage you choose to add for ordering. Use zero if the supplied quantity already contains the allowance. Record why you add any extra.
- Material price per purchase unit (USD)
- Optional price in USD per purchase unit shown by the tool. Check the actual quantity basis in your quote. Compare taxes, transport and labor separately.
How is the estimate calculated?
Net concrete = cylindrical hole volume minus embedded post volume, multiplied by hole count. Apply the explicit ordering allowance to the net volume. Hole volume per post = pi × (hole diameter / 2) squared × hole depth. Round post displacement uses pi × (post diameter / 2) squared × embedded depth. Rectangular post displacement uses actual width × height × embedded depth.
Net concrete = cylindrical hole volume minus embedded post volume, multiplied by hole count. Apply the explicit ordering allowance to the net volume.
- Convert dimensions to matching units before multiplying. Product-specific values come from your quote or label.
What does the fence post concrete calculator subtract?
Draw a small side view showing where the concrete begins and ends. If the hole contains a different material at the bottom, use the concrete-filled depth rather than counting both layers as concrete. The embedded measurement also follows the concrete contact length. The same post can displace a different amount in a deeper or shallower pour.
How do two different post sizes change the bag count?
One nominal 4 × 4 post
- Actual post 3.5 × 3.5 in
- 10 in hole diameter, 30 in of concrete and embedded length, zero allowance
- Gross volume = π × 5² × 30 ≈ 2,356.194 cu in.
- Post volume = 3.5 × 3.5 × 30 = 367.5 cu in.
- Net ≈ 1,988.694 cu in.
- Divide by 1,728 to get ≈ 1.151 cu ft.
- At 0.60 cu ft per bag, ceil(1.151 ÷ 0.60) = 2.
2 example bags per matching hole.
Check. Two bags yield 1.20 cu ft at the sample label.
One nominal 6 × 6 post
- Actual post 5.5 × 5.5 in
- 12 in diameter, 36 in of concrete and embedded length, zero allowance
- Gross = π × 6² × 36 ≈ 4,071.504 cu in.
- Displacement = 5.5 × 5.5 × 36 = 1,089 cu in.
- Net ≈ 2,982.504 cu in or 1.726 cu ft.
- At 0.60 cu ft per bag, round 2.877 up.
3 example bags for this hole.
Check. 2 bags yield 1.20 cu ft and 3 yield 1.80 cu ft at the sample yield.
Does the remaining hole volume need one bag or more?
| Hole and post | Net concrete | Example bags at 0.60 cu ft |
|---|---|---|
| 10 in hole and actual 3.5 in square post | 1.151 cu ft | 2 |
| 12 in hole and actual 5.5 in square post | 1.726 cu ft | 3 |
A cylindrical hole contains pi times radius squared times depth. Part of that space is occupied by the post. Enter the actual post dimensions and embedded length so the estimate subtracts displacement rather than counting the whole hole as concrete.
Should you group line posts and gate posts?
Sort holes into batches before buying. A gate post, a corner and an ordinary line post may not share a diameter or depth. Calculate each group and keep the per-hole figure if mixing separately. If you buy full bags for each isolated pour, that can yield a larger count than rounding the grand total once. Compare the two plans and dry handling weight.
Use the total concrete volume with the mixed yield from your selected bagged product. Hole depth, drainage details and the appropriate setting method depend on the fence and site; this tool does not prescribe them. Irregular excavation may need an explicit ordering allowance.
Will the post fit inside the measured hole?
The tool checks that the entered post fits inside the cylinder. For a rectangle, its corners need clearance too. Compare each hole with the plan rather than choosing new dimensions from the calculator. Call 811 before digging in the US and ask a qualified professional when the fence or site has structural or code requirements.
What to check before ordering
- Keep your measured estimate and purchase quantity on separate lines.
- Compare the actual purchase units, handling and delivered prices.
Frequently asked questions
Do I enter nominal post size?
Measure the actual face widths. A nominal lumber name may not equal the physical width, and the amount of concrete displaced changes with actual cross-sectional area. Record both dimensions for a rectangular post and its actual embedded length in the concrete-filled part of the hole.
Why does the calculator ask how much post is embedded?
Only the part inside the concrete displaces that concrete. Enter the overlap between post and filled depth, rather than the total post length. If the post does not extend through the full concrete layer, its embedded dimension can be shorter than the entered fill depth.
Can I round bags once for all the posts?
Yes, if usable mixed material will be shared across holes. Compute the combined volume for matching batches, then round the purchase count. If you will open only whole bags per hole and cannot share leftovers, compare a per-hole rounded quantity as a separate buying plan.
Does it choose a hole depth for my fence?
Use the depth specified for the job. This tool estimates concrete only and cannot select a safe footing or account for wind, soil or local project requirements. Confirm dimensions with the appropriate professional and contact 811 before any digging.
How many bags of concrete do I need per fence post?
First calculate the net hole volume after subtracting the embedded post. Divide that volume by your product's mixed yield per bag and round up. If batching all holes together, compare the total project volume before ordering.
Should I enter a nominal 4x4 post as four inches wide?
Use the measured dimensions of the actual post, not an assumed nominal size. Displacement depends on the cross-section and the length that is actually embedded.
Sources and editorial details
CubicPilot Editorial Team. Last content review .
- General tables of units of measurement (NIST). Reference for US customary lengths, areas and volumes.
- Before You Dig (Common Ground Alliance). Explains US utility marking and how to contact 811.
- Concrete Mix No. 1101 product data (QUIKRETE). This one product family lists approximate mixed yields by package. Check your actual bag.