Footing Concrete Calculator

Estimate concrete for rectangular or round footings from their dimensions and quantity. This footing calculator totals volume; it does not size foundations.

Project measurements

Example values are editable. Check dimensions and product labels before ordering.

count
%
USD

Price basis: per cubic yard, or per bag when entered. A blank optional quantity can be entered as 0.

Material estimate

Measured volume
0.34 m³
Measured volume
12 ft³
Measured volume
0.444 yd³
Volume with allowance
0.34 m³
Volume with allowance
0.444 yd³

Calculation trace

0.339802159104 m³ × 1 = 0.339802159104 m³

Price basis, when entered: USD per yd³.

Assumptions

  • Allowance explicitly selected: 0%.
  • Price excludes tax, delivery, labor and contingency.
  • Use actual product dimensions and manufacturer coverage.

Use the footing concrete calculator once your project specifies the dimensions. Choose a rectangular run or a round pier, multiply one footing’s volume by the count of identical footings, and apply an allowance. Calculate different sizes separately so one repeated count does not hide a change in width or depth.

Estimate concrete for rectangular or round footings from their dimensions and quantity. This footing calculator totals volume; it does not size foundations. Work from the measurements for your actual project before you check price. If another material belongs on the same order, work out its quantity separately. For companion estimates and measuring advice, see Cubic Feet to Cubic Yards: Material Volume Conversion, How to Calculate Concrete for a Slab, Concrete Bag Calculator, Fence Post Concrete Calculator, Concrete Volume Calculator. Read the CubicPilot calculation methodology for rounding, units and material assumptions.

How do you use this calculator?

  1. Select the shape if the tool offers a choice, then enter the primary measurements with their units.
  2. Enter the product’s actual label value when the form requests a yield, a package count, coverage or stock size.
  3. Choose an allowance explicitly. Read the measured and adjusted quantities before rounding any supplier order.

What should you enter?

Footing length
Primary length of the measured surface or run. Measure along the working face and keep the unit shown beside the field.
Footing width / circular diameter
Second footprint dimension, or full diameter when the circular option uses this field. Measure the concrete or material footprint itself, excluding form lumber and edging that will not be filled.
Depth
Thickness or depth of the measured material. Measure only the layer being estimated and confirm the unit before entering.
Number of footings
Number of identical units. Make a separate entry for each distinct size.
Waste / allowance
The percentage you choose to add for ordering. Use zero if the supplied quantity already contains the allowance. Record why you add any extra.
Material price per purchase unit (USD)
Optional price in USD per purchase unit shown by the tool. Check the actual quantity basis in your quote. Compare taxes, transport and labor separately.

How is the estimate calculated?

Rectangle: length × width × depth × count. Circle: pi × (diameter ÷ 2) squared × depth × count. Apply the user-entered allowance to this total.

Rectangle: length × width × depth × count. Circle: pi × (diameter ÷ 2) squared × depth × count.

  • Convert dimensions to matching units before multiplying. Product-specific values come from your quote or label.

What shapes does the footing concrete calculator use?

The useful distinction is shape. A continuous rectangular footing uses its run length times the plan’s width times its depth. A round tube uses its internal diameter and filled height. A tapered, stepped or belled footing can require more than one volume calculation. Write the shapes on the estimate so you know what each number covers.

How much concrete goes in a straight run or round pier?

Continuous rectangular run

  • 20 ft long, 12 in wide, 12 in deep
  • One run with 5% allowance
  1. 12 ÷ 12 = 1 ft for width and depth.
  2. 20 × 1 × 1 = 20 cu ft.
  3. 20 × 1.05 = 21 cu ft.
  4. 21 ÷ 27 ≈ 0.778 cu yd.

Use 21 cu ft as the adjusted order target.

Check. 21 ÷ 1.05 = 20 cu ft.

Round pier

  • 16 in internal diameter, 42 in filled height
  • One pier, zero allowance
  1. 16 ÷ 2 ÷ 12 = ⅔ ft radius.
  2. 42 ÷ 12 = 3.5 ft height.
  3. π × (⅔)² × 3.5 ≈ 4.887 cu ft.
  4. 4.887 ÷ 27 ≈ 0.181 cu yd.

Approximately 4.887 cu ft per measured pier.

Check. Multiplying the circular area of about 1.396 sq ft by 3.5 ft gives about 4.887 cu ft.

How does the footing size change volume per foot?

Volume per foot of fill for sample footing sizes
Cross sectionVolume for 1 ft
12 × 12 in rectangle1 cu ft
16 in circleabout 1.396 cu ft
24 in circleabout 3.142 cu ft

Use the rectangular option for a measured rectangular footing, or the circular option for a cylindrical footing. Multiply the volume of one identical footing by its quantity. Calculate different footing sizes separately so a repeated count does not hide changes in dimensions.

Which footings can you count as a group?

Measure the planned concrete rather than relying on the excavation label. A single long footing changes volume whenever its cross section changes. Two round piers of different diameter cannot share an input count. Keep separate lines on the purchase sheet, then combine volume only for concrete that can be ordered together.

The dimensions must come from the appropriate project design. Soil conditions, bearing loads, frost requirements and reinforcement are not determined by a volume calculator. Once the volume is known, use the bag calculator if the concrete will be mixed from bags.

Should separate concrete pours use separate estimates?

Check whether the crew and supplier intend separate pours. Transferring combined volume into bags or a delivery quote can hide handling and scheduling limits. Confirm clear access and compare the actual material count and transport. Ask a qualified professional about footing dimensions or code and call 811 before digging.

What to check before ordering

  • Keep your measured estimate and purchase quantity on separate lines.
  • Compare the actual purchase units, handling and delivered prices.

Frequently asked questions

Do I enter the radius or diameter of a pier?

Enter the diameter for the round shape. The calculation halves it to find the radius. Use the internal diameter of the form or the actual concrete dimensions given in your plan. Entering the radius in its place gives one quarter of the intended circular area.

Can I combine different pier diameters in one count?

Calculate different pier sizes separately. The count multiplies the volume of identical footings. If your drawing has several groups, record each diameter, depth and count, then add the group volumes together only when they will use the same mix and ordering arrangement.

Does a footing estimate include a slab above it?

The footing estimate covers the dimensions entered. Calculate an adjoining slab separately and check the boundary between them so the same space is counted once. For connecting shapes, use the concrete extent shown on the project plan before adding volumes.

What if a footing widens along the run?

Split a stepped run into separate measured shapes. Add the volumes before applying an order allowance. A continuous taper needs its actual cross section, which may not match either end for the whole length. Ask for clarification when the plan is unclear.

How do I calculate concrete for a round footing?

Calculate the circular area as pi times the radius squared, multiply by depth, then multiply by the number of identical footings. Use diameter and depth in compatible units.

Will this calculator tell me how deep a footing should be?

No. It estimates concrete from dimensions you supply. A qualified designer or the relevant project requirements must establish the footing dimensions.